Machine modifications and shutdowns

ACE logo

ACE Engineering GroupTechnical Insights

Assessing upgrades to existing bulk handling machines

A larger bucketwheel drive can fit the boom and deliver the required torque while the upgrade remains constrained by the slew bearing, travel gear or supporting rails. The owner needs to know whether the existing machine can deliver the proposed duty for the required further service, and what changes and evidence are needed to support that decision.

Organise the assessment around selecting a feasible option, resolving the design and installation conditions, and verifying the completed machine. Investigate anything that could change the preferred option early. The depth of assessment should follow the consequences and uncertainty of the change.

General technical information. Obtain engineering advice for your machine before applying it. Read the article disclaimer.

Before selecting the upgrade

AS 4324.1:2025 clause 1.2 recommends using the standard within a risk assessment of existing machine structures for continued use, upgrade or modification. Agree the applicable standards editions, project requirements and treatment of deterioration. Document the application, omission or variation of its requirements in the technical specification, subject to the standard’s conditions.

Define the duty and the existing machine

Describe how the extra production will be achieved. Longer operating hours, deeper cuts, higher belt speed and a wider operating range impose different demands. For example, extending daily operation at the same loads can accumulate more fatigue cycles without changing any equipment. Record the intended further service, operating positions, speeds, torque limits, expected cycles and proposed control changes.

Distinguish average production from peak reclaim flow and downstream surges. For steady conveying, material mass per unit belt length equals mass flow rate divided by belt speed. Increasing throughput at unchanged speed increases the carried material load. A proportional speed increase may leave that load broadly unchanged while affecting drives, transfers and dynamic behaviour.

Recover the design basis, drawings, equipment records, repairs and previous modifications, then compare them with the machine. A finite element model based on drawings may miss actual geometry, restraints or loading. Check receiving connections, corrosion and undocumented repairs. Inspection establishes observable condition within its access and detection limits; a satisfactory visual result alone cannot establish capacity or remaining fatigue life.

Reconcile installed masses and locations, including retained material. Use weighing or balance measurements where they resolve a material uncertainty, and record the configuration and measurement accuracy (Durst and Vogt, 1988). Weighing one state can constrain total mass and reactions without identifying every component mass or verifying every operating position.

AS 4324.1:2025 clause 5.9 applies where a modification significantly affects mass, centre of gravity, stability or balance. It requires accurate determination of the actual mass and centre of gravity, with weighing of the whole machine or at least its superstructure preferred. Define the weighing method and extent of verification in the technical specification, and meet the weighing accuracy requirement of AS 4324.1:2025 clause 5.9. A small total mass change can still matter when its position changes the moment about a pivot.

Follow the loads and compare options

For a heavier bucketwheel drive, assess the complete installed package, including mounts, guards, platforms and removals. Carry weight, torque reactions and relevant dynamic loads through the boom and connections to the supporting machine. AS 4324.1:2025 clause 1.9 bases bucketwheel digging forces on the actual drive torque and power ratings. Increased reclaiming capacity also warrants review of structural demand, rail loading and stability.

Restoring luff cylinder force with ballast does not establish that internal forces are unchanged. In a hypothetical pantograph arrangement with a centre link supporting the boom, a higher boom side weight moment requires more link force at unchanged geometry. Ballast on the separately pivoted rear assembly may restore cylinder force while that higher link force remains. The machine balance article explains the linkage assessment.

Calculate external bearing actions from the complete supported assembly. A changed internal link force alone does not establish a changed bearing resultant. For the slew bearing, consider concurrent axial and radial loads, overturning moment and the proposed load and movement spectra. Static capacity, bolt capacity and service life require distinct checks. Include mounting stiffness and condition: uneven or flexible support can concentrate loads within the raceway.

Pass consistent wheel actions and positions to the rail or wharf designer, and agree permissible movement. AS 4324.1:2025 clause 6.2 requires the technical specification to define which machine loads and load cases apply to supporting structures and rails. For crawlers, assess load distribution and ground response across the proposed configurations. Mean contact pressure alone cannot establish differential settlement or machine inclination; crawler arrangement, soil condition and repeated travel matter. The machine and infrastructure article covers these interfaces.

Screen these constraints and the retained structure’s fatigue condition before committing to equipment. A preliminary exceedance identifies work to resolve; it does not automatically rule out the upgrade. Compare a lighter package, relocation, changed supports or an assessed operating restriction with reinforcement. Include installation, temporary works, access, commissioning and infrastructure in the comparison. The result may support the preferred option, require a different arrangement or justify comparing replacement.

Before authorising installation

Establish the basis for further service

Resolve uncertainties that could reverse the selected option. For retained structure, bring together condition, repair history, past duty and proposed future loading. Define stress ranges, cycle counts and the fatigue resistance of the relevant details. Account for earlier exposure when assessing remaining life; lower calculated stress after an upgrade does not erase accumulated duty (Moczko et al., 2018).

Where duty records are incomplete, state the assumptions and test how they affect the service period or required work. Targeted load or strain measurements can improve the representation of operating loads. They do not reconstruct an unknown history by themselves. The outcome may require repair or replacement of a detail, a shorter assessed service period, changed duty or a defined inspection programme.

Give known cracks a specific disposition before relying on the affected structure. Depending on the defect and consequences, this may require repair, replacement or a fracture mechanics assessment of continued service under defined loads. Inspection intervals and acceptance criteria must follow the assessed deterioration mechanism and detection capability. More frequent inspection does not create structural capacity.

Design the transition and operating limits

Establish the operating basis while the machine awaits the shutdown, including any production increase. Plan removal and installation with the balance assessment: removing a drive or ballast changes the machine before the replacement is fitted. Include erection, dismantling, weighing and special maintenance loads, with the wind conditions and restraints applying to the work. Specify supports, restraints and jacking for each significant configuration and transition.

Define when reinforcement starts carrying load. Steel fitted to an already loaded structure cannot automatically be credited with sharing all existing dead load; unloading, preload and subsequent load changes affect the result. Put the assumed sequence into the installation instructions. Also assess installation loads and temporary welded attachments. The steel modification article develops reinforcement and load sharing details.

Where feasibility depends on an operating limit, define how it will be enforced, verified and maintained, who is responsible, and the response if it is exceeded or fails. AS 4324.1:2025 clause 3.1.2 requires credited protection and its settings to be recorded in the structural calculations and operating and maintenance manual, with its use defined in the technical specification. Nominate the applicable standard for control integrity and reliability in the specification, and determine the protection required through the risk assessment.

Any proposed omission or reduction of the requirements of AS 4324.1:2025 needs documented risk justification addressing the event, control effectiveness and consequences. Raising a luff pressure or force trip may permit loads previously interrupted. Allow for loading and movement between detection and stopping, including adequate run out at limits.

Include these changes in the site’s plant change process. Western Australia’s 2022 plant code calls for renewed risk assessment when design, use or associated work changes, consultation with the designer and manufacturer, and updated operating information. Apply the requirements relevant to the site’s jurisdiction. Set commissioning criteria before installation. AS 4324.1:2025 clause 1.11.3 requires commissioning requirements to be defined by the technical specification.

Before accepting the revised duty

Verify installed masses and locations, completed connections, relevant alignment and protection settings against the accepted design. Use a defined test plan, safe test conditions and agreed acceptance criteria. Select weighing, luff force, strain or vibration measurements to test the assumptions that matter to the assessment.

For modifications subject to AS 4324.1:2025 clause 5.9, recheck stability and balance using measured masses and satisfy its requirements for structural rechecks. If stability requirements are not met, re ballasting is required. If balance differs from the design parameters, correct it by re ballasting or demonstrate the acceptability of the actual balance by recalculation. Follow any ballast adjustment through to bearing, wheel and structural demands.

Compare measured and predicted behaviour under representative conditions and resolve material differences before releasing the revised duty. Calculations and experimental verification support decisions about operating conditions and modernisation. A familiar luff trend does not verify every internal force, and an unloaded run cannot establish performance throughout the loaded operating range.

Confirm that operating limits, inspection requirements and responses to abnormal conditions have reached the controls, manuals, procedures and people using the machine. The WA code includes inspection, testing, information and training before altered plant returns to service. Record baseline measurements under repeatable conditions; bearing clearance or deflection readings are one example.

Give the owner a clear basis for operation: the accepted configuration, duty and further service, the evidence supporting them, and the conditions and review triggers that remain. Record material assumptions and the reasons for rejecting alternatives. The next change to equipment, ballast, settings or production can then be assessed against a recoverable engineering basis.

Selected references

Standards Australia (2025). AS 4324.1:2025: Mobile equipment for continuous handling of bulk materials: Part 1: General requirements for the design of steel structures.

Durst, W. and Vogt, W. (1988). Bucket Wheel Excavator. Trans Tech Publications.

Moczko, P., Pietrusiak, D. and Rusiński, E. (2018). Material Handling and Mining Equipment: International Standards Recommendations for Design and Testing. FME Transactions.

Department of Mines, Industry Regulation and Safety, Western Australia (2022). Managing the risks of plant in the workplace: Code of practice.

Engineering support

Discuss your machine upgrade.

Contact ACE with the machine, proposed work or observed problem, available information and required timing.